Capital Master Plan

A/RES/61/251No PDF available

Who created this mandate?

A Resolution of the General Assembly, under agenda item 117Programme budget for the biennium 2006-2007, published in 2007.

What other versions does this mandate have?

11 versions · 2005–2025
This is an older version — the most recent is A/RES/80/232
  • 2025A/RES/80/232Capital Master PlanLatestCompare with previous version
  • 2024A/RES/79/246Capital Master PlanCompare with previous version
  • 2016A/RES/70/239Capital master planCompare with previous version
  • 2011A/RES/65/269Capital master planCompare with previous version
  • 2010A/RES/64/228Capital master planCompare with previous version

iVersions are identified automatically by matching titles within the same organ (~97% accuracy on a manual audit).

What subjects does this mandate have?

20 topics
AppropriationsConstructionConsultationsCost EffectivenessCostsDeveloping CountriesEconomies in TransitionFinancial ResourcesFinancingGiftsHost Country RelationsInternal OversightLetters of CreditNew York (N.y.)Office BuildingsPrivate SectorProject ExpendituresPublic SectorPurchasingVendors

What does this mandate say?

43 operative paragraphs
1
Reiterates its serious concern at the hazards, risks and deficiencies of the current condition of the United Nations Headquarters Building, which endanger the safety, health and well-being of staff, delegations, visitors and tourists;
2
Stresses the special role of the host country Government with regard to support for United Nations Headquarters in New York;
3
Recalls the current practices of host Governments with regard to support for United Nations headquarters and United Nations bodies located in their territories;
4
Takes note of the fourth annual progress report of the Secretary-General on the implementation of the capital master plan,1 the related reports of the Advisory Committee on Administrative and Budgetary Questions,2 the reports of the Secretary-General on the viable options for ensuring sufficient parking space at United Nations Headquarters3 and the plans for three additional conference rooms and viable solutions for allowing natural light into the rooms,4 the reports of the Office of Internal Oversight Services on the United Nations capital master plan for the periods from August 2003 through July 20045 and from August 2004 to July 2005,6 the report of the Office of Internal Oversight Services on its activities for the period from 1 July 2005 to 30 June 20067 and the comments of the Secretary-General thereon8 and the reports of the Board of Auditors on the capital master plan for the biennium ended 31 December 20039 and for the years ended 31 December 200410 and 31 December 2005;11
5
Also takes note of the conclusions and recommendations contained in the reports of the Advisory Committee on Administrative and Budgetary Questions;
6
Reaffirms section VI of its resolution 55/222 of 23 December 2000;
7
Also reaffirms paragraph 6 of its resolution 60/256, and calls upon the Secretary-General to explore the possibility of private donor funding for the capital master plan and to continue efforts to secure financial resources from the public and private sectors for upgrading facilities and equipment, including the participation of private companies in infrastructural improvements where such participation has no financial implications for the Organization;
8
Recalls that the acceptance of any donation should conform to the international and intergovernmental character of the Organization and should be in full compliance with the Financial Regulations and Rules of the United Nations;
9
Stresses the need for establishing sufficient cash flow for the purpose of the capital master plan, based on a practical and predictable assessment plan;
10
Decides to approve the capital master plan, including the recommended scope options, to be completed from 2006 to 2014, at a total revised project budget not to exceed 1,876.7 million United States dollars (exclusive of any credit facility fees);
11
Notes that forward pricing escalation is already included in the approved budget contained in the fourth annual progress report of the Secretary-General, and requests the Secretary-General to make every effort to avoid budget increases through sound project management practices and to ensure that the capital master plan is completed within the approved budget and the envisaged time schedule;
12
Requests the Secretary-General to submit to the General Assembly for its consideration possible options on how to remain within the approved budget of 1,876.7 million dollars in the unlikely event that it becomes evident that the costs will exceed the approved budget;
13
Decides that in the unlikely event of cost escalations beyond the approved budget of 1,876.7 million dollars, all Member States will be subject to a further assessment to meet the revised financial requirements as approved by the General Assembly;
14
Approves the funding of the capital master plan, based on a mix of one-time and equal multi-year assessments;
15
Decides that under the mixed assessment option of one-time and multi-year assessment, all assessments will be based on the regular budget scale of assessments applicable for 2007;
16
Also decides that, notwithstanding financial regulation 3.4, assessments for the capital master plan shall be issued on the same day of the first working week of January and shall be considered due and payable in full within one hundred and twenty days of that date;
17
Agrees, in this context, that in 2007 Member States will be allowed a period of sixty days, beginning on 5 January, within the period of one hundred and twenty days referred to in paragraph 16 above, to select the option of one-time or multi-year payment of their assessment on a fixed scale, as referred to in paragraph 15 above;
18
Decides, on an exceptional and ad hoc basis, unless notified otherwise by a Member State within sixty days of the issuance of the notification by the Secretary-General, to place Member States on the multi-year assessment plan for the full period of the capital master plan;
19
Also decides that once a Member State selects the option of one-time payment, that selection shall be irrevocable, unless otherwise notified to the Secretary-General by the end of the period of one hundred and twenty days referred to in paragraph 16 above;
20
Further decides to apportion, on the same day of the first working week of January for the period from 2007 to 2011, the amounts applicable, based on each Member State’s assessment option of either a one-time payment, based on its share of 1,716.7 million dollars, or equal multi-year payments over five years, in accordance with the regular budget rates of assessment applicable for 2007 for all assessments for the capital master plan, using the scale of assessments for the period 2007–2009;
21
Decides to appropriate 42 million dollars for 2007 for the design and pre-construction phases of the capital master plan, including swing-space requirements;
22
Approves the establishment of a working capital reserve of 45 million dollars under the capital master plan account, to be operated under the terms of financial regulations 3.5, 4.2 and 4.3;
23
Resolves that Member States shall make advances to the working capital reserve in accordance with the regular budget rates of assessment applicable for 2007 in the scale of assessments for the period 2007–2009;
24
Approves the establishment of a letter of credit facility as outlined in paragraphs 35 to 38 of the fourth annual progress report of the Secretary-General, pursuant to a bidding process conducted in accordance with the Financial Regulations and Rules of the United Nations;
25
Stresses that any drawdown on the letter of credit should be a last resort and solely for the purpose of funding the capital master plan;
26
Requests the Secretary-General, in this regard, to ensure that the best possible terms and conditions that preserve the interests of the Organization are negotiated with the construction manager in respect of the internationally syndicated letter of credit;
27
Also requests the Secretary-General to enter into consultations with the host country Government regarding the possibility of facilitating the establishment of the letter of credit without the imposition of fees or charges to the United Nations;
28
Further requests the Secretary-General to report to the General Assembly on the results of the negotiations and consultations and the status of the establishment of the letter of credit, in the context of his annual report on the capital master plan;
29
Notes that the establishment of the letter of credit could incur a fee of between 0.05 and 0.5 per cent of the value of the credit facility at the start of each year, and agrees that Member States will be assessed their share of the fees at the beginning of each calendar year on the basis of the regular budget scale of assessments for 2007;
30
Approves any necessary drawdown on the letter of credit, and requests the Secretary-General to advise Member States, as a matter of urgency, if a drawdown on the letter of credit is likely, preferably ninety days in advance;
31
Recalls paragraph 18 of its resolution 60/282, and decides that, notwithstanding financial regulation 3.1, any charges arising from a drawdown on the letter of credit would not be a charge on Member States that have paid in full their capital master plan assessments for the applicable period within the one hundred and twenty days of the issuance of the letters of assessment;
32
Authorizes the Secretary-General to apportion annually those charges arising from a drawdown on the letter of credit among Member States that did not pay their assessed contributions to the capital master plan in full, within the period of one hundred and twenty days specified in paragraph 16 above, based on a monthly calculation using the total charges levied during each month and the prorated share of each Member State concerned of the average total assessed contributions that are outstanding for the capital master plan during that month;
33
Requests the Secretary-General to report to the General Assembly annually on the financial aspects of the capital master plan, in particular on any outstanding contributions and on the amount of the charges specified in paragraph 32 above and the apportionment among Member States;
34
Reaffirms that the charges to be apportioned in accordance with the provisions of paragraph 32 above are expenses of the Organization to be borne by Member States in accordance with Article 17, paragraph 2, of the Charter of the United Nations;
35
Stresses the importance of oversight with respect to the implementation of the capital master plan, and requests the Board of Auditors and all other relevant oversight bodies to continue to report to the General Assembly annually on the capital master plan;
36
Requests the Secretary-General to ensure that amendments to contracts are in line with the United Nations Procurement Manual, and emphasizes that contracts should stipulate that the United Nations will not be responsible for any delays, damage or loss on the part of the contractor;
37
Reiterates its request to the Secretary-General to continue to explore ways to increase procurement opportunities for vendors from developing countries and countries with economies in transition and to take the provisions of its resolutions 54/14 of 29 October 1999, 55/247 of 12 April 2001, 57/279 of 20 December 2002, 59/288 of 13 April 2005 and 60/1 of 16 September 2005 on procurement reform fully into consideration in the implementation of the capital master plan;
38
Also reiterates its request to the Secretary-General to ensure that procurement processes are conducted in a transparent manner and in full compliance with relevant General Assembly resolutions;
39
Emphasizes to the Secretary-General the importance of effectively managing the multiple staff relocations under the approved phasing plan in order to keep the project on schedule;
40
Urges the Secretary-General to expedite the process of setting up the advisory board, reflecting wide geographical representation, so that it can begin its work as soon as possible, as provided for in section II of General Assembly resolution 57/292;
41
Requests the Secretary-General to ensure that works of art, masterpieces and other gifts are appropriately handled during all the stages of the renovation work and that all associated costs are foreseen;
42
Also requests the Secretary-General to cooperate with those Member States that wish to take care of their gifts of works of art, masterpieces and other items during the renovation period;
43
Decides that, owing to the unique and exceptional circumstances arising from the capital master plan, the decisions set out in the present resolution shall under no circumstances constitute a precedent or imply any changes to the Financial Regulations and Rules of the United Nations.

iParagraph content is machine-extracted from UN documents. For authoritative content, please refer to the official UN document.

Table of contents